Once a budget cycle is locked, a change to its forecasts goes through a change request. Your
changes collect in a draft, **Your pending changes**, until you submit them with a reason.
The budget changes only when owner or finance approves.

Owners, finance and program managers file change requests.

**The result:** your changes are with the approvers, with a reason and their impact on your program's budget, and you are told by email when they decide.

## 1. Make the change

Open the forecast and change it as usual, or add a new one. When the change would alter the
locked budget, Zeno Budget refuses the save and offers **Add to change request** (or
**Propose deleting it**). Choose it.

The change is added to **Your pending changes**:
*Added to your pending changes. The budget changes once the request is submitted and approved.*

Add as many changes as belong together. Each is a line of your draft.

> Push the Youth Mentoring summer camp from June to July and cut it to \$14,000. The budget is
> locked, so add it to my change request.

## 2. Check the impact

Open **Change requests** and select **Your pending changes**. Each line shows the forecast,
program, category, the change (for example *$18,000 → $14,000, from Jun 1 to Jul 1*) and its
effect **Over the cycle**.

**Impact** shows what the lines do to your program, category by category and month by month,
ending in **Net**, income less expense, with a headline such as *The budget spends \$4,000
less over the cycle*. Owners and finance also see the organization's cash week by week.

When the lines include balance sheet forecasts, such as a loan repayment or an asset bought,
they are listed beneath **Net**, followed by **Other cash movements** and **Cash effect**, what
the lines do to cash all together. The program's heading then adds a line beginning
*Cash effect:*.

A request of 15 lines or more groups them by category. Each group's heading gives its line
count and summed change, for example *Program Supplies · 16 lines · -\$4,800.00* (or
*1 line*), and
**Include all Program Supplies** ticks every line in it.

Tick and untick lines to see the impact of some of them. To fix a line, choose **Change**;
saving replaces that line. **Remove** takes it out. A draft whose lines are all removed is
no longer listed on **Change requests** or counted on Home as waiting; your next change goes
into it.

### What kind of request it is

Zeno Budget works out what a request is from its lines; you do not choose it. The kind shows
beside its cash effect at the top of the request, in the **What it is** column on
**Change requests**, on the change request cards, and in the emails about it.

| Kind | When |
| - | - |
| **New spending** | The lines leave less cash over the cycle, and none of the kinds below fits |
| **New funding** | The lines leave the same or more cash over the cycle. A grant added with the spending it pays for is new funding |
| **Reallocation from X to Y** | Some lines of the budget shrink and others grow by the same amount |
| **Timing change** | No program or category changes its total over the cycle: only dates move inside it |
| **Reduction** | Nothing grows: a spending cut, lost income, or both |

Each line counts against the program and category its forecast is in. A line that moves a
forecast to another program shrinks the first and grows the second. "Shrinks" and "grows" are
by size: a spending cut and lost income both shrink a budget line.

A reallocation names programs when the request touches more than one, for example
*Reallocation from Coastal Education to Youth Fellowships*, and categories when it stays in
one program: *Reallocation from Travel to Program Supplies*.

## 3. Submit it

Under **Submit for approval**, give it a **Title** (what it changes, in a few words) and a
**Why** (what the approver should know). **Needed by (optional)** is the day you need a
decision by, today or later. Choose **Submit**, or **Submit k of n** to submit only the ticked
lines; the rest stay behind in a new draft.

Owner and finance are emailed. The budget does not change until one of them approves.

A request is numbered when it is first submitted, so numbers run in the order requests went
out. A draft has no number, and a request sent back keeps its own.

The day it is needed by shows on the request, in the **Needed by** column on
**Change requests**, and in the emails about it, and is marked once it has passed. Approvers'
lists put the soonest needed first, and a reminder says how far off the day is.

You do not decide your own request while someone else in the organization may: the request
reads, for example, *You made this request, so Ruth Adler decides it.* This holds for owners
and finance too. Where you are the only owner or finance, you may decide it, and the request
then says you decided your own. See [Decide a change request](/docs/guides/decide.md#who-decides).

A request's own figure, in the **Cash effect** column on **Change requests**, at the top of
the request, on the cards and in the emails, is what its lines do to cash over the cycle,
balance sheet lines included. A program's **Net** in the impact is income less expense.

## Follow it

The request's **Timeline** records each step: submitted, comments, the decision. You can
**Add a comment**, which emails the approvers. A comment on a draft emails nobody.

* **Remind the approvers** emails them again, once a day at most.
* **Withdraw** stops the request waiting for a decision; the budget stays as it is.

You are emailed when the request is approved, partly approved, rejected or sent back.

## If it is sent back

The status reads **Sent back for revisions**, with the approver's comment. Change or remove
lines, then choose **Submit it again**.

## If it is partly approved

Some lines went into the budget and the rest were rejected. The request shows which, line by
line, as **Approved** or **Not approved**, and the byline shows how much was approved, for
example *cash effect +$6,000.00 of +$10,000.00 approved*. File a
new request for anything you still want.

## A change across two budgets

One request can change two locked budgets that are next to each other, the second starting
the day after the first ends. Moving Harborlight Institute's Harbor Fund grant payment from
November 2026 to February 2027, with FY2026 and FY2027 both locked, is one request.

The request names both budgets on the list, the cards, Home and its emails. Its page says
*This request changes two budgets: FY2026 and FY2027.*, with a table of each budget's
**Change** and **What it is**. The kind at the top is worked out across both years, so the
grant moved from November to February is a **Timing change** overall, a **Reduction** in
FY2026 and **New funding** in FY2027. The impact draws the program and the organization's cash
across both years.

Each budget's [lock page](/docs/guides/budget-cycles.md#read-what-locking-locks) lists the change
requests that touch it, with that budget's part and *Also changes* the other.

A request across two budgets can be approved only while both are locked. If one was unlocked
after you submitted, approval is refused with what to do: lock it again, or send the request
back so it can be split by date. Sending back and rejecting still work. Submitting is refused
while a budget one of the lines changes is unlocked.

If you remove the line that reaches into the second year, the request changes one budget
again.

## When a change is refused outright

A change that would reach a third locked budget, or two locked budgets with another cycle
between them, is refused. Propose it one budget at a time: end the forecast inside one budget,
and propose the rest as a new forecast in the next.

## Reverse an approved request

To turn back a request that was approved or partly approved, open it and choose
**Reverse this request**, then **Prepare reversal**. Zeno Budget makes a new draft whose lines
undo what the approval applied, from each forecast as it is now:

* a forecast it created is deleted;
* a forecast it deleted is made again;
* a forecast it changed goes back to how it was.

Lines that were not approved are left out, and so is a forecast deleted since. Nothing changes
until you submit the reversal with a reason and someone else approves it, like any request.

The reversal reads *Reversal of request 13* before its kind, and the two requests link to each
other: *Reverses request 13* on one, *Reversed by request 14* on the other (or *your draft
reversal* while it is a draft).

Owners, finance and program managers can reverse a request in their programs. It is refused
when the budget is no longer locked (change the forecasts directly instead), when a reversal is
already open, or when the request was already reversed: to undo a reversal, reverse it.

> Request 13 was a mistake. Prepare a reversal of it and show me what it would undo.