Skip to main content
A budget cycle is the stretch of dates a budget covers, usually your fiscal year. While it is open, forecasts in its dates change freely. Once it is locked, they change only through a change request. Owner and Finance open, review, lock and unlock cycles. Everyone can read Budget cycles and each cycle’s page.

Read the list

Each cycle on Budget cycles shows its status (Open, In review or Locked), its dates, and beside its name whether it is current, upcoming or ended: In November 2026, for example, Harborlight Institute’s FY2027 reads upcoming and FY2026 reads current. The label says only where today falls: a locked cycle fixes the forecasts in its dates whether it is current, upcoming or ended. A locked cycle also shows who locked it and on what day. Select a cycle’s name to open its page.

Open a cycle

  1. On Budget cycles, choose New cycle. It starts filled in with next calendar year, for example FY2027, January 1 to December 31.
  2. Check the Name, First day and Last day, then choose Open the cycle.
Cycles cannot overlap, and one can be at most two years long.

Move it to review

When programs have finished forecasting, choose Move to review. The status reads In review, which tells everyone the plan is being checked. Forecasts can still change in review; choose Reopen to go back to Open.

Read what locking locks

Open the cycle’s page from its name, or choose Lock on Budget cycles. The page reads the same whether the cycle is open, in review or locked, so finance can check the plan before anyone locks it.
  • Budget by program. Income, Expense and Net of the cycle’s forecasts over its months, a row for each top-level program and one for Not in a program, with a Total beneath. Net is income less expense, as in budget vs actual. When a program has balance sheet forecasts, such as a loan repayment or an asset bought, Other cash movements and Cash effect (the two together) are added. A retired program is left out unless it has a figure in the cycle. Select a program to open Cash flow for that program over the cycle.
  • Change requests. Every request on this budget, with its status and This budget’s change. A request that also changes the next or previous budget says Also changes and that budget’s name.
  • Balances that have not settled. Spending whose carried balance has stood a month or more, in your programs, largest first. Owners and finance can open each one and move its balance. See Balances that have not settled.
  • Cash. The organization’s Lowest closing balance and its week, projected week by week to the cycle’s end (60 weeks ahead at most), against the Cash reserve, with how many weeks end below the reserve and below zero. Select the week to open the weekly cash flow.
  • Forecast completeness. How much of what the last three years had is decided for the cycle’s year, the twelve months from its first month, how many expectations are open and what they add up to, and Open expectations, the largest 20, each with History expects and Planned, then and N more on Forecast completeness when there are more. It is the same figure as Forecast completeness shows for this cycle, and Decide open expectations opens that page on this cycle. An expectation in someone’s draft change request, not yet submitted, still counts as open. Before the cycle begins, a sentence names any days of its history year that QuickBooks has not recorded yet.
For example, Harborlight Institute’s FY2027 page might read 63% decided · 29 open · $1,170,000: the plan still lacks money that history expects, and the list below says which categories and programs. A program manager, or a viewer limited to some programs, sees only their programs’ budget. Cash reads Cash is the organization’s; your view is your programs’. Once the cycle’s first month has passed, completeness is not shown, because part of the cycle’s year is behind it. The page says, for example, FY2026 began in January 2026. Completeness judges a cycle’s year from its first month, so it is no longer judged, on this page or on Forecast completeness.

Lock it

On the cycle’s page, under Lock the budget, choose Lock. The confirmation says that changes then go through change requests, which an owner or finance approves, never the person who asked while someone else can. Choose Lock the budget to confirm. Every forecast between the cycle’s first and last day is then fixed for everyone, owners and finance included. The status reads Locked, with who locked it and when. From then on:
  • a change to a forecast’s date, amount, category, payment account or program inside the cycle becomes a line in a change request;
  • changing only a forecast’s title still goes through directly;
  • the budget as it stood at the first lock is kept, so you can always compare against the original.

Locking with expectations open

While any expectation is open, the page asks Why lock with these still open, and Lock stays unavailable until you give one. The lock is never refused for being incomplete; the reason is kept on the cycle, and its page shows it under Locked with expectations open because. With nothing open, no reason is asked for. If an expectation opens while you are on the page, the lock is refused and the reason field appears. Give a reason and lock again. Locking and unlocking have no assistant tool: they take a person’s click. An assistant can read the same page with budget_cycle_summary and tell you what is open before you lock.
What would locking FY2027 lock for Harborlight Institute? List the open expectations over $20,000.

Unlock it

Choose Unlock on Budget cycles to let forecasts change directly again. Requests already submitted stay open, and the budget as it was first locked is still kept. Unlocking clears the reason given at the lock; a later lock asks again if expectations are still open.

Delete a cycle

Delete is offered only for a cycle that was never locked, and is refused for one with change requests. Its forecasts stay; only the cycle goes.

Set the cash reserve

The Cash reserve is the least cash the organization wants on hand. Choose Change on the Cash reserve card, enter Reserve, in dollars (empty for none), and Save. The reserve shows on Home’s Budget cycle panel for everyone, on Home’s projected cash for owners and finance, and on each cycle’s page. A change request’s impact names every week that would end below it.

Set the variance threshold

Owners and finance also set the Variance threshold here, below the cash reserve. Choose Edit, enter Percent (empty for none), Dollars (empty for none) or both, and Save. Budget vs actual then marks a line Over when it is unfavorable by at least the share and the amount you set; an empty one is left out of the test. See The variance threshold.